Mains renewal around Church Road, Stretton, Burton-upon-Trent

We will soon be carrying out essential work to replace ageing water mains in your area. This will help reduce leaks and provide a more reliable water supply for the future. 

Where we will be working 

The work will take place on: 

  • Claymills Road

  • Shrewsbury Road  

  • Jordan Avenue

  • Bladon View  

Work will begin on Claymills Road and Shrewsbury Road, before moving to the remaining streets in the order listed above. 

When the work will take place 

Work is scheduled to begin on Monday 15th November 2026 and is expected to take approximately six weeks to complete. Our teams will normally work between 7:30am and 5:30pm, Monday to Friday. Occasionally, evening or weekend work may be required to reduce traffic disruption. 

Traffic changes 

To complete the work safely, some temporary traffic management will be required: 

  • Traffic Signals will be in place on Claymills Road for a period of two weeks.

  • Road closures will be in place on Shrewsbury Road, Jordan Avenue and Bladon View. 

Road closures will commence from the 15th November 2026 and be relocated as we move through and complete each street.  Clearly signed diversion routes will be in place where necessary.